  • 1st: Placing of Starter Bars
  • 2nd: Wall Panel Erection (Temporary Bracing)
  • 3rd: Shoring - Slab above Groundfloor
  • 4th: Slab Panel Erection
  • 5th: Aligning 3D Wall and Fixing Mesh - Groundfloor
  • 6th: Pouring Upper Concrete on 3D Slab
  • 7th: Shotcrete - Groundfloor
  • 8th: Wall Panel Erection - 1st Floor
  • 9th: Shoring - 1st Floor
  • 10th: Roof Panel Erection - 1st Floor
  • 11th: Finishing Wall - Groundfloor
  • 12th: Aligning 3D Wall and Fixing Mesh - 1st Floor
  • 13th: Pouring Upper Concrete on 3D Roof Slab
  • 14th: Shotcrete - 1st Floor
  • 15th: Roof Parapet
  • 16th: Removal of all Shoring
  • 17th: Finishing

Photo Gallery

   

Erection Process

Connection to Foundation & Insulation against moisture

Option 1, with Starter Bars
Option 2, with Starter Bars
Option 3, with U-Channel
Sealing against Ground Moisture

Panel preparation & Erection

Cutting of Panels
Erection of Wall Panels
Connection to Starter bar
Fixing of Splice Mesh
Door and Window Openings
Temporary bracing of Wall Panels
Stiffening of Walls without 3D Slab
Electrical and Water Pipes

Shoring & Slab panel Erection

Preparation of slab panels
Props
Shoring
Alignment and fixing with a 3D slab
3D slab
Upper concrete on 3D slabs

3D slabs for span >6m

3D Slabs with lattice girders
Additional Reinforced Beams

Different mortar application methods

Manual plastering
Hopper gun
Dry-mix concrete
Wet-mix Concrete
Finishing work

Time Consumption

Finished 3D wall
Different concrete application methods