Multi-Storey Buildings
1st: Placing of Starter Bars
2nd: Wall Panel Erection (Temporary Bracing)
3rd: Shoring - Slab above Groundfloor
4th: Slab Panel Erection
5th: Aligning 3D Wall and Fixing Mesh - Groundfloor
6th: Pouring Upper Concrete on 3D Slab
7th: Shotcrete - Groundfloor
8th: Wall Panel Erection - 1st Floor
9th: Shoring - 1st Floor
10th: Roof Panel Erection - 1st Floor
11th: Finishing Wall - Groundfloor
12th: Aligning 3D Wall and Fixing Mesh - 1st Floor
13th: Pouring Upper Concrete on 3D Roof Slab
14th: Shotcrete - 1st Floor
15th: Roof Parapet
16th: Removal of all Shoring
17th: Finishing
Photo Gallery
Erection Process
Connection to Foundation & Insulation against moisture
Option 1, with Starter Bars
Option 2, with Starter Bars
Option 3, with U-Channel
Sealing against Ground Moisture
Panel preparation & Erection
Cutting of Panels
Erection of Wall Panels
Connection to Starter bar
Fixing of Splice Mesh
Door and Window Openings
Temporary bracing of Wall Panels
Stiffening of Walls without 3D Slab
Electrical and Water Pipes
Shoring & Slab panel Erection
Preparation of slab panels
Props
Shoring
Alignment and fixing with a 3D slab
3D slab
Upper concrete on 3D slabs
3D slabs for span >6m
3D Slabs with lattice girders
Additional Reinforced Beams
Different mortar application methods
Manual plastering
Hopper gun
Dry-mix concrete
Wet-mix Concrete
Finishing work
Time Consumption
Finished 3D wall
Different concrete application methods